Electrical Load: Connected vs Demand
Learn how to organize a preliminary electrical load calculation for a dwelling, including lighting, appliances, HVAC, continuous loads, and demand.
What an electrical load calculation is for
An electrical load calculation estimates how much power a service, feeder, panel, or other distribution equipment may need to supply. It organizes lighting, receptacles, appliances, heating, cooling, motors, and other equipment into a load schedule. The result is not simply the sum of every nameplate in every situation because some loads are unlikely to operate at full output simultaneously.
A useful calculation separates the connected load from the expected or preliminary demand load. Connected load shows the total of the inputs entered. Demand load applies a stated method for diversity or noncoincident equipment. Keeping the two values visible makes the assumptions easier to review and prevents a demand estimate from being mistaken for a complete code calculation.
Connected load versus demand load
Connected load is the total rated load included in the schedule. It is useful for understanding the equipment installed and for identifying large contributors. Demand load is a planning estimate of the load expected to occur at the same time after applicable demand factors or noncoincident rules are considered. The correct method depends on the project, jurisdiction, equipment, occupancy, and applicable code section.
For example, heating and cooling equipment may be treated as noncoincident in a preliminary dwelling model when both systems are not expected to operate at their maximum at the same time. That assumption is not universal. Equipment controls, local climate, heat-pump operation, supplemental heat, and the adopted code method can change the result.
| Load group | Planning question | Data to collect |
|---|---|---|
| Lighting and general load | What area or general-use load basis applies? | Floor area, occupancy, receptacle assumptions, and jurisdiction method. |
| Appliances | Which equipment is installed and what is its rating? | Nameplate watts or VA, installation instructions, and dedicated-circuit details. |
| Heating and cooling | Can the loads be treated as noncoincident? | Equipment type, rated input, controls, and actual operating sequence. |
| Continuous loads | Does a load operate for the duration defined by the applicable rule? | Operating schedule, equipment documentation, and code treatment. |
Continuous loads and the 125 percent planning factor
A continuous load is commonly discussed as a load expected to operate for three hours or more, but the applicable code definition and calculation section control. In many conductor and overcurrent calculations, continuous load is treated at 125 percent while noncontinuous load is treated at 100 percent. That does not mean every input in a service calculation should be multiplied by 1.25 automatically.
The StructoCalc model exposes an Other Continuous Loads input and applies a 125 percent adder to that separate value so the assumption remains visible. It does not determine whether a real appliance, motor, HVAC system, or occupancy qualifies under the adopted code. Verify the correct treatment for the project and avoid applying the same factor twice.
A transparent preliminary workflow
Begin with floor area and the general-load assumptions required by the chosen method. Add small-appliance and laundry circuits when the method calls for them. Record the nameplate wattage of the water heater, range or oven, dryer, dishwasher or disposal, electric heating, cooling, and other equipment. Do not replace missing nameplate data with a guess when the actual product information is available.
Next, select the system voltage and phase so the calculator can convert watts to an estimated current. Review connected load, preliminary demand load, the larger heating or cooling input, and the continuous-load adder separately. Then compare the schedule with the panel, feeder, service, generator, or transformer being considered. If the project has motors, EV charging, solar, storage, commercial equipment, or a three-phase system, use the appropriate specialized method and professional review.
- Collect actual equipment nameplates before finalizing the load schedule.
- Keep connected load and demand load visible as separate values.
- Document every demand, diversity, and noncoincidence assumption.
- Check voltage, phase, conductor ampacity, voltage drop, grounding, protection, and local utility requirements.
Why a calculator cannot approve service size
Service sizing is affected by the adopted code, local amendments, equipment ratings, motor and HVAC rules, demand factors, conductor ampacity, voltage drop, phase balance, grounding and bonding, utility requirements, and inspection requirements. A preliminary calculator cannot verify all of those conditions from a few inputs.
Use the Electrical Load Calculator to organize a transparent first estimate and identify the loads that need review. Have the final service, feeder, panel, breaker, generator, transformer, and conductor design completed or reviewed by a qualified electrical professional. Never work on energized equipment.
Frequently asked questions
What is the difference between connected load and demand load?
Connected load is the total of the entered equipment and general loads. Demand load is a planning estimate after stated diversity, noncoincidence, or demand assumptions are applied.
Should every electrical load be multiplied by 125 percent?
No. The applicable code method determines which continuous loads receive special treatment. Document the assumption and avoid applying the same factor twice.
Why is the larger heating or cooling load used in the preliminary model?
Many preliminary dwelling methods treat heating and cooling as noncoincident. Actual equipment operation, heat-pump systems, supplemental heat, local code, and project conditions control the final treatment.
Can this calculator size my electrical service?
No. It is a preliminary planning estimate. Final service sizing requires the adopted code method, equipment data, conductor and protection checks, utility requirements, and qualified review.
Sources and further reading
- Load Calculations: Part 2 — Mike Holt Enterprises; Educational discussion of demand factors and load-calculation considerations.
- Electrical Load Calculation Single-Family — Santa Cruz County; Public permit form showing the need to document a dwelling load estimate and its limitations.
- Electrical Load Calculator — StructoCalc; The companion transparent connected-load and preliminary demand-load tool.